STATUS OF COMPLETION OF THE CENTER OF EXCELLENCE FOR ENVIRONMENTAL RESTORATION

The construction of CEER is advancing with many critical infrastructures tending towards completion. The total completion rate is 82.5%.

 

Activities

Performance for April, 2025

New Target

Actual Performance

Remarks

Faculty of Vocational Skill Acquisition

1

Substructure

 

100

100

Completed

2

Superstructure

 

100

100

Completed

3

Roof Carcass

 

100

100

Completed

4

Plastering

 

100

100

Completed

5

Ceiling grille Work

 

90

100

Completed

6

Electrical conduit

 

100

100

Completed

7

Mechanical conduit

 

100

100

Completed

8

Roof work

 

100

100

Completed

9

Window Installation

 

100

100

Completed

10

Wall screeding

 

100

100

Completed

11

Floor tiles

 

100

100

Completed

12

Cable tray Installation

 

100

100

Completed

13

Painting

 

45

50

Ongoing

14

Door installation

 

90

100

Completed

15

Suspended ceiling

 

90

95

Ongoing

16

Burglary Proof Installation

 

100

100

Completed

17

Electrical Works

 

40

45

Ongoing

18

Telecommunication cable

 

45

50

Ongoing

19

AC Outdoor/Split Indoor Unit

 

30

50

Ongoing

    

1690

 

Library

1

Substructure

 

100

100

Completed

2

Superstructure (Block works)

 

100

100

Completed

3

Steel Roof work

 

100

100

Completed

4

Electrical conduit

 

100

100

Completed

5

Mechanical conduit

 

100

100

Completed

6

Window Frame

 

100

100

Completed

7

Roof beam

 

100

100

Completed

8

Ceiling grille

 

100

100

Completed

9

Plastering

 

100

100

Completed

10

Window Glass

 

100

100

Completed

11

Roof Covering

 

100

100

Completed

12

Floor Tiling work

 

100

100

Completed

13

Wall Tiling work

 

100

100

Completed

14

Cable tray Installation

 

100

100

Completed

15

Suspended ceiling

 

100

100

Completed

16

Door installation

 

100

100

Completed

17

Painting

 

50

100

Ongoing

18

Wall Screed

 

100

100

Completed

19

Electrical works

 

70

80

Ongoing

20

Burglary Proof Installation

 

100

10

Completed

21

Telecommunication cable

 

80

80

Ongoing

22

AC Outdoor/ Split Indoor unit

 

80

80

Ongoing

    

2050

 

Faculty of Environmental Research and Development

1

Substructure

 

100

100

Completed

2

Superstructure (Block works)

 

100

100

Completed

3

Frame

 

100

100

Completed

4

Electrical conduit

 

100

100

Completed

5

Mechanical conduit

 

100

100

Completed

6

Plastering

 

100

100

Completed

7

Roof carcass

 

100

100

Completed

8

Roof covering

 

100

100

Completed

9

Suspended Ceiling/Ceiling grille

 

100

100

Completed

10

Window installation

 

100

100

Completed

11

Wall Screeding

 

100

100

Completed

12

Floor Tiling work

 

100

100

Completed

13

Wall Tiling work

 

100

100

Completed

14

Cable tray Installation

 

100

100

Completed

15

Telecommunication cable

 

80

80

Ongoing

16

Door installation

 

100

100

Completed

17

Painting

 

60

70

Ongoing

18

Electrical works

 

80

80

Ongoing

19

AC Outdoor/ Split Indoor unit

 

100

100

Completed

20

Burglary Proof Installation

 

100

100

Completed

    

1930

 

Classroom

1

Substructure

 

100

100

Completed

2

Block wall

 

100

100

Completed

3

Frame work

 

100

100

Completed

4

Roof carcass

 

100

100

Completed

5

Plastering

 

100

100

Completed

6

Electrical conduit

 

100

100

Completed

7

Mechanical conduit

 

100

100

Completed

8

Ceiling grille

 

100

100

Completed

9

Window installation

 

100

100

Completed

10

Roof covering

 

100

100

Completed

11

Floor Tiling work

 

100

100

Completed

12

Suspended ceiling

 

100

100

Completed

13

Screeding

 

100

100

Completed

14

Wall Tiling work

 

100

100

Completed

15

Door installation

 

100

100

Ongoing

16

Cable tray Installation

 

100

100

Completed

17

Telecommunication cable

 

80

80

Ongoing

18

Painting

 

60

60

Ongoing

19

Electrical works

 

70

70

Ongoing

20

AC Outdoor/ Split Indoor unit

 

100

100

Completed

21

Burglary Proof Installation

 

100

100

Completed

    

2010

 

Students Dormitory (Female)

1

Substructure

 

100

100

Completed

2

Block wall

 

100

100

Completed

3

Frame work

 

100

100

Completed

4

Suspended slab

 

100

100

Completed

5

Roof steel work

 

100

100

Completed

6

Suspended Ceiling

 

100

100

Completed

7

Plastering

 

100

100

Completed

8

Electrical conduit

 

100

100

Completed

9

Mechanical conduit

 

100

100

Completed

10

Roof cover

 

100

100

Completed

11

Floor Tiling work

 

100

100

Completed

12

Wall Tiling work

 

100

100

Completed

13

Wall Screeding

 

100

100

Completed

14

Window installation

 

100

100

Completed

15

Door installation

 

100

100

Completed

16

Cable tray Installation

 

95

100

Completed

17

Telecommunication cable

 

75

100

Completed

18

Electrical works

 

70

80

Ongoing

19

Roof Slab Felting

 

100

100

Completed

20

WC Installation

 

100

100

Completed

21

Painting

 

65

70

Ongoing

22

AC Outdoor/ Split Indoor unit

 

50

60

Ongoing

    

2110

 

Students Dormitory (Male)

1

Substructure

 

100

100

Completed

2

Superstructure (Block works)

 

100

100

Completed

3

Frame work

 

100

100

Completed

4

Suspended slab

 

100

100

Completed

5

Roof steel work

 

100

100

Completed

6

Suspended Ceiling

 

100

100

Completed

7

Plastering

 

100

100

Completed

8

Electrical conduit

 

100

100

Completed

9

Mechanical conduit

 

100

100

Completed

10

Roof cover

 

100

100

Completed

11

Floor Tiling work

 

100

100

Completed

12

Wall Screeding

 

100

100

Completed

13

Window installation

 

100

100

Completed

14

Wall Tiling work

 

100

100

Completed

15

Door Installation

 

100

100

Completed

16

Electrical Cable Tray

 

100

100

Completed

17

Telecommunication cable

 

75

100

Completed

18

Electrical wiring

 

70

80

Ongoing

19

Roof Slab Felting

 

100

100

Completed

20

WC Installation

 

100

100

Completed

21

Painting

 

65

70

Ongoing

22

AC Outdoor/ Split Indoor unit

 

50

60

Ongoing

    

2110

 

Soldiers Quarters Building:

1

Substructure

 

100

100

Completed

2

Superstructure (Block work)

 

100

100

Completed

3

Roof work

 

100

100

Completed

4

Plastering

 

100

100

Completed

5

Ceiling

 

100

100

Completed

6

Floor/wall Tiling

 

100

100

Completed

7

Painting

 

100

100

Completed

8

Door Installation

 

100

100

Completed

9

Window

 

100

100

Completed

10

Mechanical

 

95

100

Completed

11

Electrical

 

100

100

Completed

    

1100

 

3 Bedroom Duplex (10 pcs)

1

Substructure

 

100

100

Completed

2

Superstructure (Block works)

 

100

100

Completed

3

Frame

 

100

100

Completed

4

Suspended slab

 

100

100

Completed

5

Electrical conduit

 

100

100

Completed

6

Mechanical conduit

 

100

100

Completed

7

Plastering

 

100

100

Completed

8

Window frame installation

 

100

100

Completed

9

Roof Steel Carcass

 

100

100

Completed

10

Roof Covering

 

100

100

Completed

11

Aluminium Window Glass

 

100

100

Completed

12

Floor/Wall Tiling

 

100

100

Completed

13

Suspended Ceiling/grille

 

90

100

Completed

14

Wall Screed

 

85

100

Completed

15

Hand-rail

 

100

100

Completed

16

Electrical wiring

 

35

40

Ongoing

17

Door Installation

 

60

70

Ongoing

18

Painting

 

40

50

Ongoing

19

Burglary Proof Installation

 

25

40

Ongoing

    

1700

 

2 Bedroom Flat 1 (2 pcs)

1

Substructure

 

100

100

Completed

2

Superstructure (Block works)

 

100

100

Completed

3

Frame

 

100

100

Completed

4

Mechanical piping

 

100

100

Completed

5

Electrical piping

 

100

100

Completed

6

Plastering

 

100

100

Completed

7

Window frame installation

 

100

100

Completed

8

Roof Carcass

 

100

100

Completed

9

Ceiling grille

 

100

100

Completed

10

Roof Covering

 

100

100

Completed

11

Window Glass

 

100

100

Completed

12

Floor/Wall Tiling

 

100

100

Completed

13

Suspended Ceiling

 

100

100

Completed

14

Door Installation

 

100

100

Ongoing

15

Telecommunication cable

 

60

70

Ongoing

16

Electrical work

 

70

80

Ongoing

17

Painting

 

45

50

Ongoing

18

AC Outdoor/ Split Indoor unit

 

70

80

Ongoing

    

1680

 

2 Bedroom Flat 2 (4 pcs)

1

Substructure

 

100

100

Completed

2

Frame

 

100

100

Completed

3

Superstructure (Block works)

 

100

100

Completed

4

Mechanical piping

 

100

100

Completed

5

Plastering

 

100

100

Completed

6

Window Installation

 

100

100

Completed

7

Roof Steel Carcass

 

100

100

Completed

8

Roof Covering

 

100

100

Completed

9

Floor Tiling work

 

100

100

Completed

10

Suspended Ceiling

 

100

100

Completed

11

Electrical Conduit

 

100

100

Completed

12

Ceiling grille

 

100

100

Completed

13

Wall Tiling work

 

100

100

Completed

14

Screeding

 

100

100

Completed

15

Door Installation

 

100

100

Completed

16

Telecommunication cable

 

70

80

Ongoing

17

Electrical wiring

 

70

80

Ongoing

18

Painting

 

45

60

Ongoing

19

AC Outdoor/ Split Indoor unit

 

70

80

Ongoing

    

1800

 

1 Bedroom Flat (4 pcs)

1

Substructure

 

100

100

Completed

2

Frame

 

100

100

Completed

3

Superstructure (Block works)

 

100

100

Completed

4

Mechanical piping

 

100

100

Completed

5

Plastering

 

100

100

Completed

6

Roof steel work

 

100

100

Completed

7

Window Frame installation

 

100

100

Completed

8

Aluminium roof covering

 

100

100

Completed

9

Aluminium glass

 

100

100

Completed

10

Suspended ceiling

 

95

100

Ongoing

11

Floor Tiling work

 

100

100

Completed

12

Wall Tiling work

 

100

100

Completed

13

Electrical conduit

 

100

100

Completed

14

Suspended Ceiling grille

 

100

100

Completed

15

Wall screed

 

100

100

Completed

16

Door Installation

 

100

100

Completed

17

Electrical wiring

 

70

80

Ongoing

18

Telecommunication cable

 

70

80

Ongoing

19

Painting

 

45

60

Ongoing

20

AC Outdoor/ Split Indoor unit

 

80

90

Ongoing

    

1910

 

Canteen

1

Substructure

 

100

100

Completed

2

Frame

 

100

100

Completed

3

Mechanical Conduit pipe

 

100

100

Completed

4

Roof slab

 

100

100

Completed

5

Block work

 

100

100

Completed

6

Plastering

 

100

100

Completed

7

Structural Roof Truss

 

100

100

Completed

8

Aluminium window Frame

 

100

100

Completed

9

Electrical conduit piping

 

100

100

Completed

10

Wall Tiling work

 

100

100

Completed

11

Ceiling grille

 

90

100

Completed

12

Floor Tiling work

 

100

100

Completed

13

Window glass

 

100

100

Completed

14

Aluminium Roof Covering

 

100

100

Completed

15

Cable tray Installation

 

100

100

Completed

16

Door Installation

 

95

100

Completed

17

Electrical wiring

 

70

80

Ongoing

18

Painting

 

85

100

Completed

19

Telecommunication cable

 

60

70

Ongoing

20

AC Outdoor/ Split Indoor unit

 

75

80

Ongoing

    

1930

 

Shopping Plaza

1

Substructure

 

100

100

Completed

2

Frame

 

100

100

Completed

3

Block work

 

100

100

Completed

4

Plastering

 

100

100

Completed

5

 Roof Covering

 

100

100

Completed

6

Electrical conduit

 

100

100

Completed

7

Mechanical conduit

 

100

100

Completed

8

Suspended Ceiling/grille

 

100

100

Completed

9

Aluminium window

 

100

100

Completed

10

Floor Tiling work

 

100

100

Completed

11

Wall tiling

 

100

100

Completed

12

Electrical wiring

 

70

80

Ongoing

13

Door Installation

 

100

100

Completed

14

Roof slab felting

 

100

100

Completed

15

Painting

 

85

100

Completed

16

Telecommunication cable

 

70

80

Ongoing

17

AC Outdoor/ Split Indoor unit

 

70

80

Ongoing

    

1640

 

Clinic

1

Substructure

 

100

100

Completed

2

Block works

 

100

100

Completed

3

Frame

 

100

100

Completed

4

Plastering

 

100

100

Completed

5

Roof covering

 

100

100

Completed

6

Window installation

 

100

100

Completed

7

Suspended Ceiling grille

 

100

100

Completed

8

Electrical conduit

 

100

100

Completed

9

Mechanical conduit

 

100

100

Completed

10

Wall Screeding

 

100

100

Completed

11

Suspended Ceiling

 

100

100

Completed

12

Floor Tiling work

 

100

100

Completed

13

Wall Tiling work

 

100

100

Completed

14

Door Installation

 

100

100

Completed

15

Cable tray Installation

 

100

100

Completed

16

Electrical wiring

 

70

80

Ongoing

17

Telecommunication cable

 

70

80

Ongoing

18

Painting

 

75

80

Ongoing

19

AC Outdoor/ Split Indoor unit

 

70

80

Ongoing

    

1820

 

Fencing/ External work:

1

Block work

 

100

100

Completed

2

Excavation/ backfilling

 

100

100

Completed

3

Concrete blinding for fence foundation

 

100

100

Completed

4

Rendering

 

45

55

Ongoing

5

Column/Beam work

 

100

100

Completed

6

Retaining wall

 

100

100

Completed

7

Painting

 

90

100

Ongoing

    

655

 

Road Work

1

Earth work

 

95

100

Completed

2

Asphalt

 

95

100

Completed

3

Concrete Kerbs

 

95

100

Completed

    

300

 

DRAINAGE WORK

1

Installation of Precast drain

 

95

100

Completed

2

External Drainage/Cover

 

60

70

Ongoing

Admin Block

1

Substructural Work

 

100

100

Completed

2

Block works

 

100

100

Completed

3

Frame

 

100

100

Completed

4

Suspended slab

 

100

100

Completed

5

Electrical conduit

 

100

100

Completed

6

Mechanical conduit

 

100

100

Ongoing

7

Staircase

 

100

100

Completed

8

Plastering

 

100

100

Completed

9

Ceiling grille

 

70

80

Ongoing

10

Wall Screeding

 

95

100

Ongoing

11

Cable tray Installation

 

100

100

Completed

12

Aluminium window Frame

 

100

100

Completed

13

Wall Tiling

 

100

100

Completed

14

Curtainwall Frame Installation

 

100

100

Completed

15

Lift Installation

 

50

60

Ongoing

16

Ceiling cassette AC Installation

 

100

100

Ongoing

17

Roof Slab Felting

 

100

100

Completed

18

Door Installation

 

20

30

Ongoing

19

Floor Tiling

 

100

100

Ongoing

20

Refrigerant Pipes

 

100

100

Ongoing

21

Painting

 

40

60

Ongoing

22

AC Duct Installation

 

100

100

Completed

23

Handrail

 

30

40

Ongoing

24

Electrical work

 

40

50

Ongoing

25

Telecommunication cable

 

45

50

Ongoing

    

2170

 

Auditorium

1

Substructural Work

 

100

100

Completed

2

Super structure (Gallery)

 

100

100

Completed

3

Frame

 

100

100

Completed

4

Electrical conduit

 

100

100

Ongoing

5

Mechanical conduit

 

100

80

Ongoing

6

Roof slab

 

100

100

Completed

7

Block works

 

100

100

Completed

8

Plastering

 

100

100

Completed

9

Roof Steel Work

 

100

100

Completed

10

Window frame installation

 

100

100

Completed

11

Window glass

 

100

100

Ongoing

12

Ceiling grille

 

100

100

Ongoing

13

Cable tray Installation

 

100

100

Ongoing

14

Roof Slab Felting

 

100

100

Completed

15

Roof Covering

 

90

100

Completed

16

Ceiling AC Cassette Installation

 

100

100

Ongoing

17

Fibreglass Installation

 

100

100

Ongoing

18

Acoustic wall cladding

 

70

75

Ongoing

19

Floor Tiling

 

85

100

Ongoing

20

Wall tiles

 

90

100

Ongoing

21

Refrigerant Pipes

 

45

60

Ongoing

22

Painting

 

45

50

Ongoing

23

Electrical work

 

80

100

Ongoing

24

AC Duct Installation

 

85

100

Ongoing

25

Handrail

 

85

90

Ongoing

26

Suspended Ceiling

 

45

50

Ongoing

27

Telecommunication cable

 

35

50

Ongoing

28

Door Installation

 

80

90

Ongoing

29

Wall screed

 

70

80

Ongoing

    

2625

 

CLUB HOUSE

1

Sub-structure

 

100

100

Completed

2

Mechanical conduit piping

 

100

100

Completed

3

Electrical conduit piping

 

100

100

Completed

4

Suspended slab

 

100

100

Completed

5

Roof Slab

 

100

100

Completed

6

Block work

 

100

100

Completed

7

Plastering

 

100

100

Completed

8

Aluminium Window

 

100

100

Completed

9

Roof steel work

 

100

100

Completed

10

Ceiling grille

 

95

100

Completed

11

Wall Tiling

 

100

100

Completed

12

Floor Tiling

 

95

100

Completed

13

Aluminium Roof Covering

 

100

100

Completed

14

Cable tray installation

 

100

100

Completed

15

Wall screed

 

80

100

Completed

16

Painting

 

45

50

Ongoing

17

Door Installation

 

90

100

Completed

18

Roof Slab Felting

 

100

100

Completed

19

Electrical work

 

50

60

Ongoing

20

Suspended ceiling

 

30

40

Ongoing

21

Telecommunication

 

40

50

Ongoing

    

1900

 

GATE HOUSE

1

Sub-structure

 

100

100

Completed

2

Suspended slab

 

100

100

Completed

3

Frame

 

100

100

Completed

4

Superstructure (Block works)

 

100

100

Completed

5

Plastering

 

100

100

Completed

6

Wall Screeding

 

85

100

Ongoing

7

Electrical conduit

 

100

100

Completed

8

Mechanical conduit

 

80

100

Completed

9

Window installation

 

100

100

Completed

10

Roof Slab Felting

 

100

100

Completed

11

Painting

 

100

100

Completed

    

1100

 

POWER HOUSE

1

Sub-structure

 

100

100

Completed

2

Frame

 

100

100

Completed

3

Roof Slab

 

100

100

Completed

4

Window installation

 

100

100

Completed

5

Plastering

 

100

100

Completed

6

Block work

 

100

100

Completed

7

Screeding

 

100

100

Completed

8

Roof Slab Felting

 

100

100

Completed

9

Painting

 

70

80

Ongoing

10

Roof Slab Felting

 

100

100

Completed

11

Generator set placement

 

80

100

Completed

12

Door Installation

 

80

100

Completed

13

Electrical work

 

40

50

Ongoing

14

Acoustic wall cladding

 

100

100

Completed

15

Painting

 

60

70

Ongoing

    

1400

 

WATER BOARD

1

Sub-structure

 

100

100

Completed

2

Superstructure (Block works)

 

100

100

Completed

3

Frame

 

100

100

Completed

4

Roof slab

 

100

100

Completed

5

Plastering

 

100

100

Completed

6

Electrical conduit

 

100

100

Completed

7

Mechanical conduit

 

100

100

Ongoing

8

Roof Slab Felting

 

100

100

Completed

9

Wall Screeding

 

100

100

Ongoing

10

Roof Slab Felting

 

70

80

Ongoing

11

Door Installation

 

30

40

Ongoing

12

Roof Slab Felting

 

40

60

Ongoing

    

1080

 

ELEVATED WATER TANK

1

Sub-structure

 

100

100

Completed

2

Tank stanchion Installation

 

100

100

Completed

    

200

 

 

FIRE FIGHTING WATER POOL/RAW WATER TANK FOUNDATION

1

Sub-structure

 

100

100

Completed

2

Superstructure

 

70

80

Ongoing

    

180

 

PARKING LOT

1

Parking lot 1 and 2 (interlockings)

 

100

100

Completed

    

100

 

EXTERNAL WORK

1

Land scaping (grassing)

 

45

50

Ongoing

2

Tree planting

 

45

50

Ongoing

3

Mechanical plumbing work (pipes, chambers)

 

90

100

Completed

4

Interlocking walkway

 

50

60

Ongoing

5

External cable work

 

80

100

Completed

    

360

 

FOOTBALL PITCH

1

Earth work/Preparation

 

90

100

Completed

2

Drainage

 

100

100

Completed

3

Track Asphalt Road

 

100

100

Completed

4

Grassing

 

20

30

Ongoing

    

330

 

 

MICROBIOLOGY/CHEMISTRY WET LAB

1

Sub-structure

 

100

100

Completed

2

Frames

 

95

100

Completed

3

Block work

 

100

100

Completed

4

Structural steel roof

 

80

100

Completed

5

Plastering

 

60

70

Ongoing

6

Window Frame installation

 

80

100

Completed

    

570

 

ENGINEERED BIOCELL/INCINERATION AREA

1

Sub-structure

 

100

100

Completed

2

Frames

 

100

100

Completed

3

Slab

 

100

100

Completed

4

Staircase

 

100

100

Completed

5

Structural steel roof

 

95

100

Completed

6

Block work

 

90

100

Completed

    

600

 

TABLE TENNIS/BASKET BALL/BADMINTON COURT

1

Sub-structure

 

100

100

Completed

2

Solar light plinth

 

80

100

Completed

3

Basketball Hoop stand

 

80

100

Completed

    

300

 
Scroll to Top