STATUS OF COMPLETION OF THE CENTER OF EXCELLENCE FOR ENVIRONMENTAL RESTORATION
The construction of CEER is advancing with many critical infrastructures tending towards completion. The total completion rate is 91%.
Activities |
Status of activities |
||||
New Target |
Actual Performance |
Remarks |
|||
Faculty of Vocational Skill Acquisition |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Superstructure |
100 |
100 |
Completed |
|
3 |
Roof Carcass |
100 |
100 |
Completed |
|
4 |
Plastering |
100 |
100 |
Completed |
|
5 |
Ceiling grille Work |
100 |
100 |
Completed |
|
6 |
Electrical conduit |
100 |
100 |
Completed |
|
7 |
Mechanical conduit |
100 |
100 |
Completed |
|
8 |
Roof work |
100 |
100 |
Completed |
|
9 |
Window Installation |
100 |
100 |
Completed |
|
10 |
Wall screeding |
100 |
100 |
Completed |
|
11 |
Floor tiles |
100 |
100 |
Completed |
|
12 |
Cable tray Installation |
100 |
100 |
Completed |
|
13 |
Painting |
75 |
63 |
Ongoing |
|
14 |
Door installation |
100 |
100 |
Completed |
|
15 |
Suspended ceiling |
100 |
100 |
Ongoing |
|
16 |
Burglary Proof Installation |
100 |
100 |
Completed |
|
17 |
Electrical Works |
70 |
65 |
Ongoing |
|
18 |
Telecommunication cable |
75 |
60 |
Ongoing |
|
19 |
AC Outdoor/Split Indoor Unit |
85 |
70 |
Ongoing |
|
1805 |
1748 |
||||
Library |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
3 |
Steel Roof work |
100 |
100 |
Completed |
|
4 |
Electrical conduit |
100 |
100 |
Completed |
|
5 |
Mechanical conduit |
100 |
100 |
Completed |
|
6 |
Window Frame |
100 |
100 |
Completed |
|
7 |
Roof beam |
100 |
100 |
Completed |
|
8 |
Ceiling grille |
100 |
100 |
Completed |
|
9 |
Plastering |
100 |
100 |
Completed |
|
10 |
Window Glass |
100 |
100 |
Completed |
|
11 |
Roof Covering |
100 |
100 |
Completed |
|
12 |
Floor Tiling work |
100 |
100 |
Completed |
|
13 |
Wall Tiling work |
100 |
100 |
Completed |
|
14 |
Cable tray Installation |
100 |
100 |
Completed |
|
15 |
Suspended ceiling |
100 |
100 |
Completed |
|
16 |
Door installation |
100 |
100 |
Completed |
|
17 |
Painting |
100 |
100 |
Ongoing |
|
18 |
Wall Screed |
100 |
100 |
Completed |
|
19 |
Electrical works |
80 |
80 |
Ongoing |
|
20 |
Burglary Proof Installation |
100 |
100 |
Completed |
|
21 |
Telecommunication cable |
80 |
80 |
Ongoing |
|
22 |
AC Outdoor/ Split Indoor unit |
80 |
80 |
Ongoing |
|
2050 |
2050 |
||||
Faculty of Environmental Research and Development |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
3 |
Frame |
100 |
100 |
Completed |
|
4 |
Electrical conduit |
100 |
100 |
Completed |
|
5 |
Mechanical conduit |
100 |
100 |
Completed |
|
6 |
Plastering |
100 |
100 |
Completed |
|
7 |
Roof carcass |
100 |
100 |
Completed |
|
8 |
Roof covering |
100 |
100 |
Completed |
|
9 |
Suspended Ceiling/Ceiling grille |
100 |
100 |
Completed |
|
10 |
Window installation |
100 |
100 |
Completed |
|
11 |
Wall Screeding |
100 |
100 |
Completed |
|
12 |
Floor Tiling work |
100 |
100 |
Completed |
|
13 |
Wall Tiling work |
100 |
100 |
Completed |
|
14 |
Cable tray Installation |
100 |
100 |
Completed |
|
15 |
Telecommunication cable |
80 |
80 |
Ongoing |
|
16 |
Door installation |
100 |
100 |
Completed |
|
17 |
Painting |
70 |
70 |
Ongoing |
|
18 |
Electrical works |
80 |
80 |
Ongoing |
|
19 |
AC Outdoor/ Split Indoor unit |
100 |
100 |
Completed |
|
20 |
Burglary Proof Installation |
100 |
100 |
Completed |
|
1930 |
1930 |
||||
Classroom |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Block wall |
100 |
100 |
Completed |
|
3 |
Frame work |
100 |
100 |
Completed |
|
4 |
Roof carcass |
100 |
100 |
Completed |
|
5 |
Plastering |
100 |
100 |
Completed |
|
6 |
Electrical conduit |
100 |
100 |
Completed |
|
7 |
Mechanical conduit |
100 |
100 |
Completed |
|
8 |
Ceiling grille |
100 |
100 |
Completed |
|
9 |
Window installation |
100 |
100 |
Completed |
|
10 |
Roof covering |
100 |
100 |
Completed |
|
11 |
Floor Tiling work |
100 |
100 |
Completed |
|
12 |
Suspended ceiling |
100 |
100 |
Completed |
|
13 |
Screeding |
100 |
100 |
Completed |
|
14 |
Wall Tiling work |
100 |
100 |
Completed |
|
15 |
Door installation |
100 |
100 |
Ongoing |
|
16 |
Cable tray Installation |
100 |
100 |
Completed |
|
17 |
Telecommunication cable |
80 |
80 |
Ongoing |
|
18 |
Painting |
60 |
60 |
Ongoing |
|
19 |
Electrical works |
70 |
70 |
Ongoing |
|
20 |
AC Outdoor/ Split Indoor unit |
100 |
100 |
Completed |
|
21 |
Burglary Proof Installation |
100 |
100 |
Completed |
|
2010 |
2010 |
||||
Students Dormitory (Female) |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Block wall |
100 |
100 |
Completed |
|
3 |
Frame work |
100 |
100 |
Completed |
|
4 |
Suspended slab |
100 |
100 |
Completed |
|
5 |
Roof steel work |
100 |
100 |
Completed |
|
6 |
Suspended Ceiling |
100 |
100 |
Completed |
|
7 |
Plastering |
100 |
100 |
Completed |
|
8 |
Electrical conduit |
100 |
100 |
Completed |
|
9 |
Mechanical conduit |
100 |
100 |
Completed |
|
10 |
Roof cover |
100 |
100 |
Completed |
|
11 |
Floor Tiling work |
100 |
100 |
Completed |
|
12 |
Wall Tiling work |
100 |
100 |
Completed |
|
13 |
Wall Screeding |
100 |
100 |
Completed |
|
14 |
Window installation |
100 |
100 |
Completed |
|
15 |
Door installation |
100 |
100 |
Completed |
|
16 |
Cable tray Installation |
100 |
100 |
Completed |
|
17 |
Telecommunication cable |
100 |
100 |
Completed |
|
18 |
Electrical works |
80 |
80 |
Ongoing |
|
19 |
Roof Slab Felting |
100 |
100 |
Completed |
|
20 |
WC Installation |
100 |
100 |
Completed |
|
21 |
Painting |
70 |
70 |
Ongoing |
|
22 |
AC Outdoor/ Split Indoor unit |
50 |
60 |
Ongoing |
|
2110 |
2110 |
||||
Students Dormitory (Male) |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
3 |
Frame work |
100 |
100 |
Completed |
|
4 |
Suspended slab |
100 |
100 |
Completed |
|
5 |
Roof steel work |
100 |
100 |
Completed |
|
6 |
Suspended Ceiling |
100 |
100 |
Completed |
|
7 |
Plastering |
100 |
100 |
Completed |
|
8 |
Electrical conduit |
100 |
100 |
Completed |
|
9 |
Mechanical conduit |
100 |
100 |
Completed |
|
10 |
Roof cover |
100 |
100 |
Completed |
|
11 |
Floor Tiling work |
100 |
100 |
Completed |
|
12 |
Wall Screeding |
100 |
100 |
Completed |
|
13 |
Window installation |
100 |
100 |
Completed |
|
14 |
Wall Tiling work |
100 |
100 |
Completed |
|
15 |
Door Installation |
100 |
100 |
Completed |
|
16 |
Electrical Cable Tray |
100 |
100 |
Completed |
|
17 |
Telecommunication cable |
100 |
100 |
Completed |
|
18 |
Electrical wiring |
80 |
80 |
Ongoing |
|
19 |
Roof Slab Felting |
100 |
100 |
Completed |
|
20 |
WC Installation |
100 |
100 |
Completed |
|
21 |
Painting |
70 |
70 |
Ongoing |
|
22 |
AC Outdoor/ Split Indoor unit |
60 |
60 |
Ongoing |
|
2110 |
2110 |
||||
Soldiers Quarters Building: |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Superstructure (Block work) |
100 |
100 |
Completed |
|
3 |
Roof work |
100 |
100 |
Completed |
|
4 |
Plastering |
100 |
100 |
Completed |
|
5 |
Ceiling |
100 |
100 |
Completed |
|
6 |
Floor/wall Tiling |
100 |
100 |
Completed |
|
7 |
Painting |
100 |
100 |
Completed |
|
8 |
Door Installation |
100 |
100 |
Completed |
|
9 |
Window |
100 |
100 |
Completed |
|
10 |
Mechanical |
100 |
100 |
Completed |
|
11 |
Electrical |
100 |
100 |
Completed |
|
1100 |
1100 |
||||
3 Bedroom Duplex (10 pcs) |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
3 |
Frame |
100 |
100 |
Completed |
|
4 |
Suspended slab |
100 |
100 |
Completed |
|
5 |
Electrical conduit |
100 |
100 |
Completed |
|
6 |
Mechanical conduit |
100 |
100 |
Completed |
|
7 |
Plastering |
100 |
100 |
Completed |
|
8 |
Window frame installation |
100 |
100 |
Completed |
|
9 |
Roof Steel Carcass |
100 |
100 |
Completed |
|
10 |
Roof Covering |
100 |
100 |
Completed |
|
11 |
Aluminium Window Glass |
100 |
100 |
Completed |
|
12 |
Floor/Wall Tiling |
100 |
100 |
Completed |
|
13 |
Suspended Ceiling/grille |
100 |
100 |
Completed |
|
14 |
Wall Screed |
100 |
100 |
Completed |
|
15 |
Hand-rail |
100 |
100 |
Completed |
|
16 |
Electrical wiring |
40 |
40 |
Ongoing |
|
17 |
Door Installation |
70 |
70 |
Ongoing |
|
18 |
Painting |
50 |
50 |
Ongoing |
|
19 |
Burglary Proof Installation |
40 |
40 |
Ongoing |
|
1700 |
1700 |
||||
2 Bedroom Flat 1 (2 pcs) |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
3 |
Frame |
100 |
100 |
Completed |
|
4 |
Mechanical piping |
100 |
100 |
Completed |
|
5 |
Electrical piping |
100 |
100 |
Completed |
|
6 |
Plastering |
100 |
100 |
Completed |
|
7 |
Window frame installation |
100 |
100 |
Completed |
|
8 |
Roof Carcass |
100 |
100 |
Completed |
|
9 |
Ceiling grille |
100 |
100 |
Completed |
|
10 |
Roof Covering |
100 |
100 |
Completed |
|
11 |
Window Glass |
100 |
100 |
Completed |
|
12 |
Floor/Wall Tiling |
100 |
100 |
Completed |
|
13 |
Suspended Ceiling |
100 |
100 |
Completed |
|
14 |
Door Installation |
100 |
100 |
Ongoing |
|
15 |
Telecommunication cable |
70 |
70 |
Ongoing |
|
16 |
Electrical work |
80 |
80 |
Ongoing |
|
17 |
Painting |
50 |
50 |
Ongoing |
|
18 |
AC Outdoor/ Split Indoor unit |
80 |
80 |
Ongoing |
|
1680 |
1680 |
||||
2 Bedroom Flat 2 (4 pcs) |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Frame |
100 |
100 |
Completed |
|
3 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
4 |
Mechanical piping |
100 |
100 |
Completed |
|
5 |
Plastering |
100 |
100 |
Completed |
|
6 |
Window Installation |
100 |
100 |
Completed |
|
7 |
Roof Steel Carcass |
100 |
100 |
Completed |
|
8 |
Roof Covering |
100 |
100 |
Completed |
|
9 |
Floor Tiling work |
100 |
100 |
Completed |
|
10 |
Suspended Ceiling |
100 |
100 |
Completed |
|
11 |
Electrical Conduit |
100 |
100 |
Completed |
|
12 |
Ceiling grille |
100 |
100 |
Completed |
|
13 |
Wall Tiling work |
100 |
100 |
Completed |
|
14 |
Screeding |
100 |
100 |
Completed |
|
15 |
Door Installation |
100 |
100 |
Completed |
|
16 |
Telecommunication cable |
80 |
80 |
Ongoing |
|
17 |
Electrical wiring |
80 |
80 |
Ongoing |
|
18 |
Painting |
60 |
60 |
Ongoing |
|
19 |
AC Outdoor/ Split Indoor unit |
80 |
80 |
Ongoing |
|
1800 |
1800 |
||||
1 Bedroom Flat (4 pcs) |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Frame |
100 |
100 |
Completed |
|
3 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
4 |
Mechanical piping |
100 |
100 |
Completed |
|
5 |
Plastering |
100 |
100 |
Completed |
|
6 |
Roof steel work |
100 |
100 |
Completed |
|
7 |
Window Frame installation |
100 |
100 |
Completed |
|
8 |
Aluminium roof covering |
100 |
100 |
Completed |
|
9 |
Aluminium glass |
100 |
100 |
Completed |
|
10 |
Suspended ceiling |
100 |
100 |
Ongoing |
|
11 |
Floor Tiling work |
100 |
100 |
Completed |
|
12 |
Wall Tiling work |
100 |
100 |
Completed |
|
13 |
Electrical conduit |
100 |
100 |
Completed |
|
14 |
Suspended Ceiling grille |
100 |
100 |
Completed |
|
15 |
Wall screed |
100 |
100 |
Completed |
|
16 |
Door Installation |
100 |
100 |
Completed |
|
17 |
Electrical wiring |
80 |
80 |
Ongoing |
|
18 |
Telecommunication cable |
80 |
80 |
Ongoing |
|
19 |
Painting |
60 |
60 |
Ongoing |
|
20 |
AC Outdoor/ Split Indoor unit |
90 |
90 |
Ongoing |
|
1910 |
1910 |
||||
Canteen |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Frame |
100 |
100 |
Completed |
|
3 |
Mechanical Conduit pipe |
100 |
100 |
Completed |
|
4 |
Roof slab |
100 |
100 |
Completed |
|
5 |
Block work |
100 |
100 |
Completed |
|
6 |
Plastering |
100 |
100 |
Completed |
|
7 |
Structural Roof Truss |
100 |
100 |
Completed |
|
8 |
Aluminium window Frame |
100 |
100 |
Completed |
|
9 |
Electrical conduit piping |
100 |
100 |
Completed |
|
10 |
Wall Tiling work |
100 |
100 |
Completed |
|
11 |
Ceiling grille |
100 |
100 |
Completed |
|
12 |
Floor Tiling work |
100 |
100 |
Completed |
|
13 |
Window glass |
100 |
100 |
Completed |
|
14 |
Aluminium Roof Covering |
100 |
100 |
Completed |
|
15 |
Cable tray Installation |
100 |
100 |
Completed |
|
16 |
Door Installation |
95 |
100 |
Completed |
|
17 |
Electrical wiring |
80 |
80 |
Ongoing |
|
18 |
Painting |
100 |
100 |
Completed |
|
19 |
Telecommunication cable |
70 |
70 |
Ongoing |
|
20 |
AC Outdoor/ Split Indoor unit |
80 |
80 |
Ongoing |
|
1930 |
1930 |
||||
Shopping Plaza |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Frame |
100 |
100 |
Completed |
|
3 |
Block work |
100 |
100 |
Completed |
|
4 |
Plastering |
100 |
100 |
Completed |
|
5 |
Roof Covering |
100 |
100 |
Completed |
|
6 |
Electrical conduit |
100 |
100 |
Completed |
|
7 |
Mechanical conduit |
100 |
100 |
Completed |
|
8 |
Suspended Ceiling/grille |
100 |
100 |
Completed |
|
9 |
Aluminium window |
100 |
100 |
Completed |
|
10 |
Floor Tiling work |
100 |
100 |
Completed |
|
11 |
Wall tiling |
100 |
100 |
Completed |
|
12 |
Electrical wiring |
80 |
80 |
Ongoing |
|
13 |
Door Installation |
100 |
100 |
Completed |
|
14 |
Roof slab felting |
100 |
100 |
Completed |
|
15 |
Painting |
100 |
100 |
Completed |
|
16 |
Telecommunication cable |
80 |
80 |
Ongoing |
|
17 |
AC Outdoor/ Split Indoor unit |
80 |
80 |
Ongoing |
|
1640 |
1640 |
||||
Clinic |
|||||
1 |
Substructure |
100 |
100 |
Completed |
|
2 |
Block works |
100 |
100 |
Completed |
|
3 |
Frame |
100 |
100 |
Completed |
|
4 |
Plastering |
100 |
100 |
Completed |
|
5 |
Roof covering |
100 |
100 |
Completed |
|
6 |
Window installation |
100 |
100 |
Completed |
|
7 |
Suspended Ceiling grille |
100 |
100 |
Completed |
|
8 |
Electrical conduit |
100 |
100 |
Completed |
|
9 |
Mechanical conduit |
100 |
100 |
Completed |
|
10 |
Wall Screeding |
100 |
100 |
Completed |
|
11 |
Suspended Ceiling |
100 |
100 |
Completed |
|
12 |
Floor Tiling work |
100 |
100 |
Completed |
|
13 |
Wall Tiling work |
100 |
100 |
Completed |
|
14 |
Door Installation |
100 |
100 |
Completed |
|
15 |
Cable tray Installation |
100 |
100 |
Completed |
|
16 |
Electrical wiring |
80 |
80 |
Ongoing |
|
17 |
Telecommunication cable |
80 |
80 |
Ongoing |
|
18 |
Painting |
80 |
80 |
Ongoing |
|
19 |
AC Outdoor/ Split Indoor unit |
80 |
80 |
Ongoing |
|
1820 |
1820 |
||||
Fencing/ External work: |
|||||
1 |
Block work |
100 |
100 |
Completed |
|
2 |
Excavation/ backfilling |
100 |
100 |
Completed |
|
3 |
Concrete blinding for fence foundation |
100 |
100 |
Completed |
|
4 |
Rendering |
55 |
55 |
Ongoing |
|
5 |
Column/Beam work |
100 |
100 |
Completed |
|
6 |
Retaining wall |
100 |
100 |
Completed |
|
7 |
Painting |
90 |
100 |
Ongoing |
|
655 |
655 |
||||
Road Work |
|||||
1 |
Earth work |
100 |
100 |
Completed |
|
2 |
Asphalt |
100 |
100 |
Completed |
|
3 |
Concrete Kerbs |
100 |
100 |
Completed |
|
300 |
300 |
||||
DRAINAGE WORK |
|||||
1 |
Installation of Precast drain |
100 |
100 |
Completed |
|
2 |
External Drainage/Cover |
70 |
70 |
Ongoing |
|
Admin Block |
|||||
1 |
Substructural Work |
100 |
100 |
Completed |
|
2 |
Block works |
100 |
100 |
Completed |
|
3 |
Frame |
100 |
100 |
Completed |
|
4 |
Suspended slab |
100 |
100 |
Completed |
|
5 |
Electrical conduit |
100 |
100 |
Completed |
|
6 |
Mechanical conduit |
100 |
100 |
Ongoing |
|
7 |
Staircase |
100 |
100 |
Completed |
|
8 |
Plastering |
100 |
100 |
Completed |
|
9 |
Ceiling grille |
80 |
80 |
Ongoing |
|
10 |
Wall Screeding |
100 |
100 |
Ongoing |
|
11 |
Cable tray Installation |
100 |
100 |
Completed |
|
12 |
Aluminium window Frame |
100 |
100 |
Completed |
|
13 |
Wall Tiling |
100 |
100 |
Completed |
|
14 |
Curtainwall Frame Installation |
100 |
100 |
Completed |
|
15 |
Lift Installation |
60 |
60 |
Ongoing |
|
16 |
Ceiling cassette AC Installation |
100 |
100 |
Ongoing |
|
17 |
Roof Slab Felting |
100 |
100 |
Completed |
|
18 |
Door Installation |
30 |
30 |
Ongoing |
|
19 |
Floor Tiling |
100 |
100 |
Ongoing |
|
20 |
Refrigerant Pipes |
100 |
100 |
Ongoing |
|
21 |
Painting |
60 |
60 |
Ongoing |
|
22 |
AC Duct Installation |
100 |
100 |
Completed |
|
23 |
Handrail |
30 |
40 |
Ongoing |
|
24 |
Electrical work |
50 |
50 |
Ongoing |
|
25 |
Telecommunication cable |
50 |
50 |
Ongoing |
|
2170 |
2170 |
||||
Auditorium |
|||||
1 |
Substructural Work |
100 |
100 |
Completed |
|
2 |
Super structure (Gallery) |
100 |
100 |
Completed |
|
3 |
Frame |
100 |
100 |
Completed |
|
4 |
Electrical conduit |
100 |
100 |
Ongoing |
|
5 |
Mechanical conduit |
80 |
80 |
Ongoing |
|
6 |
Roof slab |
100 |
100 |
Completed |
|
7 |
Block works |
100 |
100 |
Completed |
|
8 |
Plastering |
100 |
100 |
Completed |
|
9 |
Roof Steel Work |
100 |
100 |
Completed |
|
10 |
Window frame installation |
100 |
100 |
Completed |
|
11 |
Window glass |
100 |
100 |
Ongoing |
|
12 |
Ceiling grille |
100 |
100 |
Ongoing |
|
13 |
Cable tray Installation |
100 |
100 |
Ongoing |
|
14 |
Roof Slab Felting |
100 |
100 |
Completed |
|
15 |
Roof Covering |
100 |
100 |
Completed |
|
16 |
Ceiling AC Cassette Installation |
100 |
100 |
Ongoing |
|
17 |
Fibreglass Installation |
100 |
100 |
Ongoing |
|
18 |
Acoustic wall cladding |
75 |
75 |
Ongoing |
|
19 |
Floor Tiling |
100 |
100 |
Ongoing |
|
20 |
Wall tiles |
100 |
100 |
Ongoing |
|
21 |
Refrigerant Pipes |
60 |
60 |
Ongoing |
|
22 |
Painting |
50 |
50 |
Ongoing |
|
23 |
Electrical work |
100 |
100 |
Ongoing |
|
24 |
AC Duct Installation |
100 |
100 |
Ongoing |
|
25 |
Handrail |
90 |
90 |
Ongoing |
|
26 |
Suspended Ceiling |
50 |
50 |
Ongoing |
|
27 |
Telecommunication cable |
50 |
50 |
Ongoing |
|
28 |
Door Installation |
90 |
90 |
Ongoing |
|
29 |
Wall screed |
80 |
80 |
Ongoing |
|
2625 |
2625 |
||||
CLUB HOUSE |
|||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Mechanical conduit piping |
100 |
100 |
Completed |
|
3 |
Electrical conduit piping |
100 |
100 |
Completed |
|
4 |
Suspended slab |
100 |
100 |
Completed |
|
5 |
Roof Slab |
100 |
100 |
Completed |
|
6 |
Block work |
100 |
100 |
Completed |
|
7 |
Plastering |
100 |
100 |
Completed |
|
8 |
Aluminium Window |
100 |
100 |
Completed |
|
9 |
Roof steel work |
100 |
100 |
Completed |
|
10 |
Ceiling grille |
100 |
100 |
Completed |
|
11 |
Wall Tiling |
100 |
100 |
Completed |
|
12 |
Floor Tiling |
100 |
100 |
Completed |
|
13 |
Aluminium Roof Covering |
100 |
100 |
Completed |
|
14 |
Cable tray installation |
100 |
100 |
Completed |
|
15 |
Wall screed |
80 |
100 |
Completed |
|
16 |
Painting |
50 |
50 |
Ongoing |
|
17 |
Door Installation |
100 |
100 |
Completed |
|
18 |
Roof Slab Felting |
100 |
100 |
Completed |
|
19 |
Electrical work |
60 |
60 |
Ongoing |
|
20 |
Suspended ceiling |
40 |
40 |
Ongoing |
|
21 |
Telecommunication |
50 |
50 |
Ongoing |
|
1900 |
1900 |
||||
GATE HOUSE |
|||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Suspended slab |
100 |
100 |
Completed |
|
3 |
Frame |
100 |
100 |
Completed |
|
4 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
5 |
Plastering |
100 |
100 |
Completed |
|
6 |
Wall Screeding |
100 |
100 |
Ongoing |
|
7 |
Electrical conduit |
100 |
100 |
Completed |
|
8 |
Mechanical conduit |
100 |
100 |
Completed |
|
9 |
Window installation |
100 |
100 |
Completed |
|
10 |
Roof Slab Felting |
100 |
100 |
Completed |
|
11 |
Painting |
100 |
100 |
Completed |
|
1100 |
|||||
POWER HOUSE |
|||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Frame |
100 |
100 |
Completed |
|
3 |
Roof Slab |
100 |
100 |
Completed |
|
4 |
Window installation |
100 |
100 |
Completed |
|
5 |
Plastering |
100 |
100 |
Completed |
|
6 |
Block work |
100 |
100 |
Completed |
|
7 |
Screeding |
100 |
100 |
Completed |
|
8 |
Roof Slab Felting |
100 |
100 |
Completed |
|
9 |
Painting |
80 |
80 |
Ongoing |
|
10 |
Roof Slab Felting |
100 |
100 |
Completed |
|
11 |
Generator set placement |
100 |
100 |
Completed |
|
12 |
Door Installation |
100 |
100 |
Completed |
|
13 |
Electrical work |
50 |
50 |
Ongoing |
|
14 |
Acoustic wall cladding |
100 |
100 |
Completed |
|
15 |
Painting |
70 |
70 |
Ongoing |
|
1400 |
1400 |
||||
WATER BOARD |
|||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Superstructure (Block works) |
100 |
100 |
Completed |
|
3 |
Frame |
100 |
100 |
Completed |
|
4 |
Roof slab |
100 |
100 |
Completed |
|
5 |
Plastering |
100 |
100 |
Completed |
|
6 |
Electrical conduit |
100 |
100 |
Completed |
|
7 |
Mechanical conduit |
100 |
100 |
Ongoing |
|
8 |
Roof Slab Felting |
100 |
100 |
Completed |
|
9 |
Wall Screeding |
100 |
100 |
Ongoing |
|
10 |
Roof Slab Felting |
80 |
80 |
Ongoing |
|
11 |
Door Installation |
40 |
40 |
Ongoing |
|
12 |
Roof Slab Felting |
60 |
60 |
Ongoing |
|
1080 |
1080 |
||||
ELEVATED WATER TANK |
|||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Tank stanchion Installation |
100 |
100 |
Completed |
|
200 |
200 |
||||
|
FIRE FIGHTING WATER POOL/RAW WATER TANK FOUNDATION |
||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Superstructure |
80 |
80 |
Ongoing |
|
180 |
180 |
||||
PARKING LOT |
|||||
1 |
Parking lot 1 and 2 (interlockings) |
100 |
100 |
Completed |
|
100 |
|||||
EXTERNAL WORK |
|||||
1 |
Land scaping (grassing) |
50 |
50 |
Ongoing |
|
2 |
Tree planting |
50 |
50 |
Ongoing |
|
3 |
Mechanical plumbing work (pipes, chambers) |
100 |
100 |
Completed |
|
4 |
Interlocking walkway |
60 |
60 |
Ongoing |
|
5 |
External cable work |
100 |
100 |
Completed |
|
360 |
360 |
||||
FOOTBALL PITCH |
|||||
1 |
Earth work/Preparation |
100 |
100 |
Completed |
|
2 |
Drainage |
100 |
100 |
Completed |
|
3 |
Track Asphalt Road |
100 |
100 |
Completed |
|
4 |
Grassing |
30 |
30 |
Ongoing |
|
330 |
330 |
||||
|
MICROBIOLOGY/CHEMISTRY WET LAB |
||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Frames |
100 |
100 |
Completed |
|
3 |
Block work |
100 |
100 |
Completed |
|
4 |
Structural steel roof |
100 |
100 |
Completed |
|
5 |
Plastering |
70 |
70 |
Ongoing |
|
6 |
Window Frame installation |
100 |
100 |
Completed |
|
570 |
570 |
||||
ENGINEERED BIOCELL/INCINERATION AREA |
|||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Frames |
100 |
100 |
Completed |
|
3 |
Slab |
100 |
100 |
Completed |
|
4 |
Staircase |
100 |
100 |
Completed |
|
5 |
Structural steel roof |
100 |
100 |
Completed |
|
6 |
Block work |
100 |
100 |
Completed |
|
600 |
600 |
||||
TABLE TENNIS/BASKET BALL/BADMINTON COURT |
|||||
1 |
Sub-structure |
100 |
100 |
Completed |
|
2 |
Solar light plinth |
100 |
100 |
Completed |
|
3 |
Basketball Hoop stand |
100 |
100 |
Completed |
|
300 |
300 |