STATUS OF COMPLETION OF THE CENTER OF EXECELLENCE FOR ENVIRONMENTAL RESTORATION

S/N Work Fronts Target %Completion Remarks
1.00 Faculty of Vocational Skill Acquisition     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Superstructure 100 100 Completed
c Roof carcass 100 100 Completed
d Plastering 100 100 Completed
e Ceiling grile Work 100 100  
f Electrical conduit 80 90  
g Mechanical conduit 80 90  
h Roof work 100 100 Completed
i Window Installation 100 100 Completed
j Wall screed 60 70  
2.00 Library     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Superstructure (Block works) 100 100 Completed
c Steel Roof work 100 100 Completed
d Electrical conduit 70 90  
e Mechanical conduit 70 90  
f Frame 100 100 Completed
g Roof beam 100 100 Completed
h Ceiling grille 20 50  
i Plastering 80 100  
3.00 Faculty of Environmental Research and Development     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Superstructure (Block works) 100 100 Completed
c Frame 100 100 Completed
d Electrical conduit 90 95  
e Mechanical conduit 70 80  
f Plastering 100 100 Completed
g Roof carcass 100 100 Completed
h Roof covering 100 100 Completed
i Suspended Ceiling 90 100  
j Window  installation 100 100 Completed
k Wall Screed 90 100  
l Floor Tiling work 100 100 Completed
m Wall Tiling work 100 100 Completed
4.00 Classroom     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Block wall 100 100 Completed
c Frame work 100 100 Completed
d Roof carcass 100 100 Completed
e Plastering 100 100 Completed
f Electrical conduit 100 100  
g Mechanical conduit 85 90  
h Ceiling grile 90 100  
i Window installation 100 100 Completed
j Roof covering 100 100 Completed
k Floor Tiling work 100 100 Completed
l Suspended ceiling 85 90  
m Screed 90 90  
n Wall Tiling work 95 100  
o Door installation 40 50  
5.00 Students Dormitory (Female)     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Block wall 100 100 Completed
c Frame work 100 100 Completed
d Suspended slab 100 100 Completed
e Roof steel work 100 100 Completed
f Suspended Ceiling 95 100  
g Plastering 100 100 Completed
h Electrical conduit 90 95  
i Mechanical conduit 70 80  
j Roof cover 100 100 Completed
k Floor Tiling work 100 100 Completed
l Wall Tiling work 100 100 Completed
m Wall Screed 80 90  
n Window  installation 100 100 Completed
o Door installation 40 60  
p Cable tray Installation 50 70  
6.00 Students Dormitory (Male)     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Superstructure (Block works) 100 100 Completed
c Frame work 100 100 Completed
d Suspended slab 100 100 Completed
e Roof steel work 100 100  
f Suspended Ceiling 90 100  
g Plastering 100 100 Completed
h Electrical conduit 70 80  
i Mechanical conduit 70 80  
j Roof cover 100 100 Completed
k Floor Tiling work 100 100 Completed
l Wall Screed 80 90  
m Window installation 100 100 Completed
n Wall Tiling work 50 70  
o Door Installation 50 50  
7.00 Soldiers Quarters Building:     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Superstructure (Block work) 100 100 Completed
c Roof work 100 100 Completed
d Plastering 100 100 Completed
e Ceiling 95 100  
f Tiling 100 100 Completed
g Painting 100 100 Completed
h Door 100 100 Completed
i Window 100 100 Completed
j Mechanical 86 100  
k Electrical 86 100  
8.00 3 bedroom Duplex (10 pcs)     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Superstructure (Block works) 100 100 Completed
c Frame 100 100 Completed
d Suspended slab 100 100 Completed
e Electrical conduit 50 60  
f Mechanical conduit 70 80  
g Plastering 30 40  
h Window frame installation 40 50  
i Roof Steel Carcass 30 50  
j Roof Covering 10 30  
9.00 2 Bedroom Flat 1 (2 pcs)     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Superstructure (Block works) 100 100 Completed
c Frame 100 100 Completed
d Mechanical 50 70  
e Plastering 50 60  
f Window frame installation 100 100 Completed
g Roof carcass 0 0  
10.00 2 Bedroom Flat 2 (4 pcs)     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Frame 100 100 Completed
c Superstructure (Block works) 100 100 Completed
d Mechanical 50 70  
e Plastering 70 100  
f Window Installation 25 50  
g Roof Steel Carcass 85 100  
h Roof covering 85 70  
i Ceiling grille 30 50  
11.00 1 Bedroom Flat  (4 pcs)     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Frame 100 100 Completed
c Superstructure (Block works) 100 100 Completed
d Mechanical 70 80  
e Plastering 90 100  
f Roof steel work 100 100 Completed
g Window Frame installation 100 100 Completed
h Aluminum roof covering 100 100  
i Aluminum glass 100 100 Completed
j Suspended ceiling 40 50  
k Floor Tiling work 60 60  
l Electrical conduit 90 100  
m Suspended Ceiling grile 80 100  
n Wall screed 15 30  
12.00 Canteen     Sub-structural work
a Substructure 100 100 Completed
b Frame 100 100 Completed
c Mechanical 70 80  
d Roof slab 100 100 Completed
e Block work 95 100  
13.00 Shopping Plaza     Sub-structural work
a Substructure 100 100 Completed
b Frame 100 100 Completed
c Block work 10 50  
14.00 Clinic     Sub-structural/Super-structural work
a Substructure 100 100 Completed
b Block works 100 100 Completed
c Frame 100 100 Completed
d Plastering 100 100 Completed
e Roof covering 100 100 Completed
f Window  installation 100 100 Completed
g Suspended Ceiling grile 100 100 Completed
h Electrical conduit 100 100 Completed
i Mechanical conduit 70 100  Completed
j Wall Screed 70 100  Completed
k Suspended Ceiling 90 100  completed
l Floor Tiling work 100 100 Completed
m Wall Tiling work 90 100  completed
15.00 Fencing/ external work:     Sub-structural/Super-structural work
a Block work 100 100 Completed
b Excavation/ backfilling 100 100 Completed
c Concrete blinding for fence foundation 100 100 Completed
d Rendering 20 30  Ongoing
e Column/Beam work 100 100 Completed
f Retaining wall 100 100  Completed
16.00 Road Work     Earth work
a Earth work 85 90  Ongoing
b Asphalts 80 85  ongoing
c Concrete Kerbs 85 90  Ongoing
17.00 DRAINAGE WORK      
a Installation of Precast drain 90 95  ongoing
b External Drainage/Cover 50 60  ongoing
18.00 Admin Block     Sub-structural/Super-structural work
a Sub-structural Work 100 100 Completed
b Block works 85 100  completed
c Frame 100 100 Completed
d Suspended slab 100 100 Completed
e Electrical conduit 75 80  ongoing
f Mechanical conduit 70 80  ongoing
g Staircase 100 100 Completed
h Plastering 50 50 Ongoing
i Ceiling grille 30 50  Ongoing
19.00 Auditorium     Sub-structural work
a Sub-structural Work 100 100 Completed
b Super structure (Gallery) 100 100 Completed
c Frame 100 100 Completed
d Electrical conduit 70 80  Ongoing
e Mechanical conduit 70 80  Ongoing
f Roof slab 100 100 Completed
g Block works 100 100  Completed
h Plastering 90 100  completed
20.00 CLUB HOUSE     Sub-structural work
a Sub-structure 100 100 Completed
b Mechanical conduit 70 80  Ongoing
c Frame 100 100 Completed
d Suspended slab 100 100 Completed
e Roof Slab 100 100 Completed
f Block work 60 70  Ongoing
21.00 GATE HOUSE     Sub-structural/Super-structural work
a Sub-structure 100 100 Completed
b Suspended slab 100 100 Completed
c Frame 100 100 Completed
d Superstructure (Block works) 100 100 Completed
e Plastering 100 100 Completed
f Wall Screed 60 80  Ongoing
g Electrical conduit 80 90   Ongoing
h Mechanical conduit 80 90   Ongoing
i Window installation 100 100 Completed
22.00 POWER HOUSE      
a Sub-structure 100 100 Sub-structural work
b Frame 100 100 Completed
c Roof Slab 100 100 Completed
d Window installation 100 100 Completed
e Plastering 100 100 Completed
f Block work 100 100 Completed
23.00 WATER BOARD      
a Sub-structure 100 100 Sub-structural work
b Superstructure (Block works) 100 100 Completed
c Frame 100 100 Completed
d Roof slab 100 100 Completed
e Plastering 100 100 Completed
f Electrical conduit 80 90   Ongoing
g Mechanical conduit 80 90   Ongoing
h Window installation 100 100 Completed
i Wall Screed 45 50   Ongoing
24.00 ELEVATED WATER TANK      
a Sub-structure 90 100 Sub-structural work
b Tank stanchion Installation 80 100 Super-structural work
25.00 FIRE FIGHTING WATER POOL/RAW WATER TANK FOUNDATION      
a Sub-structure 80 100 Sub-structural/Super-structural work
26.00 PARKING LOT      
a Parking lot 1 and 2 (inter locks) 70 100 Completed
27.00 EXTERNAL WORK      
a Landscaping (grassing) 20 30  Ongoing