Project Summary Scope
To undertake Clean-up and Remediation of impacted shoreline areas and mud flats through agitation, recovery, and appropriate disposal of recovered crude oil / oily wastes using all necessary equipment and logistics methods. That may be required for effective delivery to the standard set for the HYPREP SCAT Team by NOSDRA & NUPRC regulatory agencies. Target cleanup is 20% oiling in the observation pit. Recovered oil to be disposed at licensed waste management facilities.
SLC 001
DESCRIPTION: Shoreline Clean-up in B/Dere zone 1
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 16.5ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 96,800m3
CONTRACTOR: Geoquest Int, Services Ltd
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 37.86%
SLC 002
DESCRIPTION: Shoreline Clean-up in B/Dere zone 3
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 26.0ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 25,080m3
CONTRACTOR: Welltime Limited
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 11.84%
SLC 003
DESCRIPTION: Shoreline Clean-up in B/Dere zone 4
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 73.6ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 2,640m3
CONTRACTOR: Fortified City Technologies Nig Ltd
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 6.67%
SLC 004
DESCRIPTION: Shoreline Clean-up in B/Dere zone 5
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 23ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 39,600m3
CONTRACTOR: Dinetuks Nigeria Limited with Lamor Corporation
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has Commenced
PERCENTAGE OF WORK COMPLETION: 67.98%
SLC 005
DESCRIPTION: Shoreline Clean-up in B/Dere zone 6
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 43.3ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 14520m3
CONTRACTOR: Ekhiam Ventures Ltd
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced
PERCENTAGE OF WORK COMPLETION: 31.05%
SLC 006
DESCRIPTION: Shoreline Clean-up in B/Dere zone 7
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 33.7ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 22,440m3
CONTRACTOR: Rivdel Engineering Consultancy Limited
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced
PERCENTAGE OF WORK COMPLETION: 13.35%
SLC 007
DESCRIPTION: Shoreline Clean-up in B/Dere zone 8
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 19.3ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 5,280m3
CONTRACTOR: Navante Oil and Gas Company Limited
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced
PERCENTAGE OF WORK COMPLETION: 7.78%
SLC 008
DESCRIPTION: Shoreline Clean-up in B/Dere zone 9
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 26.7ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 23,760m3
CONTRACTOR: Yok Daniel Nigeria Limited
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced
PERCENTAGE OF WORK COMPLETION: 17.65%
SLC 009
DESCRIPTION: Shoreline Clean-up in K/Dere zone 1
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 23ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT:
CONTRACTOR: Sures Global Resources Nig Ltd.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 5.00%
SLC 010
DESCRIPTION: Shoreline Clean-up in Goi zone 2
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 28.9ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 11,000m3
CONTRACTOR: MUS Engineering Consults ltd.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 5.56%
SLC 011
DESCRIPTION: Shoreline Clean-up in K/Dere zone 3
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 33.8ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 21,120m3
CONTRACTOR: Geo-Kooy Environmental Services.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 5.00%
SLC 012
DESCRIPTION: Shoreline Clean-up in K/Dere zone 4
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 29.4ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 10,560m3
CONTRACTOR: ZGM Investment Group of Companies Ltd.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Pre-mobilization Activities.
PERCENTAGE OF WORK COMPLETION: 3.00%
SLC 013
DESCRIPTION: Shoreline Clean-up in K/Dere zone 5
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 40.5ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 80,520m3
CONTRACTOR: Cagewox Dot Net Limited.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 5.00%
SLC 014
DESCRIPTION: Shoreline Clean-up in K/Dere zone 6
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 61.3ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 3,960m3
CONTRACTOR: DLK Oil & Gas Environmental Services Ltd.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 5.00%
SLC 015
DESCRIPTION: Shoreline Clean-up in K/Dere zone 7
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 9.2ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 50,160m3
CONTRACTOR: Bussdor & Company Limited.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Pre-mobilization Activities.
PERCENTAGE OF WORK COMPLETION: 3.00%
SLC 016
DESCRIPTION: Shoreline Clean-up in K/Dere zone 8
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 50.7ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 36,960m3
CONTRACTOR: Galembic Int’l Ltd.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 6.99%
SLC 017
DESCRIPTION: Shoreline Clean-up in K/Dere zone 9
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 35.1ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT:
CONTRACTOR: Carlton Concept Projects Ltd.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 5.00%
SLC 018
DESCRIPTION: Shoreline Clean-up in K/Dere zone 10
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 51.9ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT:
CONTRACTOR: Amazing Environmental Solution Int’l Limited.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 5.00%
SLC 019
DESCRIPTION: Shoreline Clean-up in K/Dere zone 11
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 37.0ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT:
CONTRACTOR: Aniset Integrated Services with Shiwinis Integrated Services.
SCOPE SUMMARY: Cleanup of oil impacted mangrove ecosystem.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 5.00%
SLC 020
DESCRIPTION: Shoreline Clean-up in Kpor zone 1
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 14.3ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 18,700m3
CONTRACTOR: Serock Energy Services and Bessiyi Nigeria Ltd.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Pre-mobilization Activities.
PERCENTAGE OF WORK COMPLETION: 3.00%
SLC 021
DESCRIPTION: Shoreline Clean-up in Kpor zone 2
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 27.9ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 4,640m3
CONTRACTOR: Chavyn Nigeria Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 6.67%
SLC 022
DESCRIPTION: Shoreline Clean-up in Kpor zone 3
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 20.6ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 20,900m3
CONTRACTOR: Wiz China World Engineering Ltd.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 6.11%
SLC 023
DESCRIPTION: Shoreline Clean-up in Bomu zone 1A
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 99.6ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT:
CONTRACTOR: Iris Eagle Ltd.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 30.64%
SLC 024
DESCRIPTION: Shoreline Clean-up in Bomu zone 1B
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 79.9ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 9,900m3
CONTRACTOR: Transcend Construction Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 26.99%
SLC 025
DESCRIPTION: Shoreline Clean-up in Bomu zone 2A
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 103.5ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT:
CONTRACTOR: Trutech Engineering Consultant Services Ltd.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 31.14%
SLC 026
DESCRIPTION: Shoreline Clean-up in Bomu zone 2B
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 62.2ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 3,850m3
CONTRACTOR: Abduganas Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has Commenced.
PERCENTAGE OF WORK COMPLETION: 16.15%
SLC 027
DESCRIPTION: Shoreline Clean-up in Bomu zone 3A
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 48.7ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 35,200m3
CONTRACTOR: Step Engineering Services Ltd in partnership with Oakridge Environmental Engineering Inc.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 24.91%
SLC 028
DESCRIPTION: Shoreline Clean-up in Bomu zone 3B
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 183.8ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 82,280m3
CONTRACTOR: Sikodris Nigeria Limited in Partnership with Ken Vic Moore Biz Ventures Nig Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 38.80%
SLC 029
DESCRIPTION: Shoreline Clean-up in Bomu zone 4A
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 78.8ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 9,900m3
CONTRACTOR: Camyota Limited in partnership with Ksplan Consult Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 19.04%
SLC 030
DESCRIPTION: Shoreline Clean-up in Bomu zone 4B
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 94.8ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 9,900m3
CONTRACTOR: Icren Services Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 22.52%
SLC 031
DESCRIPTION: Shoreline Clean-up in Bomu zone 5A
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 134.2ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 33,000m3
CONTRACTOR: Brant Technologies Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 19.25%
SLC 032
DESCRIPTION: Shoreline Clean-up in Bomu zone 5B
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 69.3ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT:
CONTRACTOR: Gbereogoni Oil and Gas Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 15.19%
SLC 033
DESCRIPTION: Shoreline Clean-up in Goi zone 1
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 28.3ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 36,300m3
CONTRACTOR: Prime Logistic Integrated Network Ltd.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 36.72%
SLC 034
DESCRIPTION: Shoreline Clean-up in Goi zone 2
LOCATION: Gokana LGA
AREA (ha) FOR AGITATION AND FLUSHING: 28.9ha
VOLUME (cubic meter) ARTISANAL REFINERY AREAS FOR TREATMENT: 11,000m3
CONTRACTOR: TMCH Group Limited.
SCOPE SUMMARY: Clean up of oil impacted mangrove ecosystem and artisanal refinery areas.
STATUS OF WORK ACTIVITIES: Cleanup has commenced.
PERCENTAGE OF WORK COMPLETION: 7.22%