Land Remediation Phase 2

Phase 2 Remediation Works

Project Summary Scope

  • To carryout Site Characterization and Assessment
  • To carryout Remediation of Hydrocarbon Polluted Soil and Groundwater on assessed sites

SMR 001

UNEP CODE: 004 -OO1
LOCATION: Ajeokpori Ogale Eleme LGA
SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294973; Northing: 532184
CONTRACTOR: Beachstone Limited
SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.
STATUS OF WORK ACTIVITIES:
The contractor has achieved a completion percentage 12% having carried out the following activities:
1. Mobilized to site.
2. Site characterization/assessment field sampling and data collection completed.
3. Site office setup completed.
4. Biocell construction ongoing.
5. Submitted site characterization report and Remediation Action Plan (RAP) for Review.
6. Review of the site characterization report and RAP ongoing.

SMR 002

UNEP CODE: 004 -OO1
LOCATION: Ajeokpori Ogale Eleme LGA
SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294815 ; Northing: 531988
CONTRACTOR: Avondale Services and Supplies Limited
SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.
STATUS OF WORK ACTIVITIES:
The contractor has achieved a completion percentage 14.5% having carried out the following activities:
1. Mobilized to site.
2. Site characterization/assessment field sampling and data collection completed.
3. Site office setup completed.
4. Submitted initial site characterization report and RAP for review.
5. Biocell construction completed.
6. Review of the site characterization report and RAP ongoing.

SMR 003

UNEP CODE: 004 -OO1
LOCATION: Ajeokpori Ogale Eleme LGA
SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294603 ; Northing: 531772
CONTRACTOR: Earthpro Unique Integrated Limited
SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.
STATUS OF WORK ACTIVITIES:
The contractor has achieved a completion percentage 27.5% having carried out the following activities:
1. Mobilized to site.
2. Site characterization/assessment field sampling and data collection completed.
3. Site office setup completed.
4. Submitted Site Characterization Report and RAP for review.
5. The contractor has been given provisional approval by NOSDRA to commence the Remediation phase of the works after review of documents.
6. Biocell construction completed.
7. Commencement of remediation works.

SMR 004

UNEP CODE: 004 -OO1
LOCATION: Ajeokpori Ogale Eleme LGA
SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294865 ; Northing: 532284
CONTRACTOR: Newline West Africa Limited
SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.
STATUS OF WORK ACTIVITIES:
The contractor has achieved a completion percentage 40.5% having carried out the following activities:
1. Mobilized to site.
2. Site characterization/assessment field sampling and data collection completed.
3. Site office setup completed.
4. Biocell construction completed.
5. Submitted site characterization report and RAP for review.
6. The contractor has been given provisional approval by NOSDRA to commence the remediation phase of the works after review of documents.
7. Commencement of remediation works.

SMR 005

UNEP CODE: 004 -OO1
LOCATION: Site A: Ajeokpori Ogale Eleme LGA ; Site B : Okuluebu, Ogale, Eleme LGA
SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294722 ; Northing: 532149
CONTRACTOR: Ecosafe Services Ltd
SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.
STATUS OF WORK ACTIVITIES:
The contractor has achieved a completion percentage 12% having carried out the following activities:
Mobilized to site.
Completed site office for site A.
Completed site characterization/assessment field sampling and data collection for sites A and B.
Submitted initial copy of site characterization and RAP for review.
Review of the site characterization report and RAP ongoing.
Biocell construction ongoing.

SMR 006

UNEP CODE: 004 -OO1

LOCATION:  Ajeokpori Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294609; Northing: 532063

CONTRACTOR: Icren Services Limited

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 21% having carried out the following activities:

  1. Mobilized to the site
  2. Completion of Site Office
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has obtained full regulatory approval for their site characterization report and RAP.
  5. Remediation Action Phase ongoing: Ex-situ treatment method: Excavation and Treatment of contaminated soils

SMR 007

UNEP CODE: 004 -OO1

LOCATION:  Ajeokpori Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294518; Northing: 531987

CONTRACTOR: Geokooy Environmental Services Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 11.5% having carried out the following activities:

  1. Mobilized to the site
  2. Completed site office setup.
  3. Site characterization/assessment field sampling and data collection completed. The Characterization Report and RAP have been submitted and are currently under review.
  4. Biocell Construction completed

SMR 008

UNEP CODE: 004 -OO1

LOCATION:  Ajeokpori Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294435; Northing: 531954

CONTRACTOR: Cagewox Dot Net Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage 11.5% having carried out the following activities:

  1. Mobilized to the site
  2. Completed site office setup.
  3. Site characterization/assessment field sampling and data collection completed. The Characterization Report and RAP have been submitted and are currently under review.
  4. Biocell construction Completed

SMR 009

UNEP CODE: 004 -OO1

LOCATION:  Ajeokpori Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294387; Northing: 531881

CONTRACTOR: Foxtrot O & G Company Nigeria Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 11.5% having carried out the following activities:

  1. Mobilized to the site
  2. Completed site office setup.
  3. Site characterization/assessment field sampling and data collection completed. The Characterization Report and RAP have been submitted and are currently under review.
  4. Biocell Construction completed

SMR 010

UNEP CODE: 004 -OO1

LOCATION:  Ajeokpori Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294318; Northing: 531906

CONTRACTOR: Lamor Corp Ab and Dinetuks Nigeria Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 13% having carried out the following activities:

  1. Mobilized to site.
  2. Completed site office
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has obtained full regulatory approval for their site characterization report and RAP to commence remedial action.
  5. Continuation of the Remediation Action Phase: insitu treatment method: Installation of biosparging injection wells

SMR011

UNEP CODE: 004 -OO1

LOCATION:  Ajeokpori Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294178; Northing: 531869

CONTRACTOR: Stefanutti Stocks Hapel Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 13.5% having carried out the following activities:

  1. Mobilized to the site.
  2. Completed Office setup
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has obtained conditional approval regulatory approval for their site characterization report and RAP to commence remedial action.
  5. Remediation works have not commenced because a fence has been erected around the work areas of the site, obstructing access to the work area.

SMR 012

UNEP CODE: 004 -OO1

LOCATION:  Ajeokpori Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294178; Northing: 531869

CONTRACTOR: Fibow Petroleum Environmental Engineering Consult Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 10% having carried out the following activities:

  1. Mobilized to site
  2. Office Setup Completed
  3. Site Characterization/assessment Field sampling and data collection completed
  4. Awaiting the submission of the Site Characterization Report and RAP for review
  5. Biocell Construction Completed

SMR 013

UNEP CODE: 004 -OO1

LOCATION:  Ajeokpori Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294219; Northing: 531733

CONTRACTOR: Nopec Energy Services Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 12% having carried out the following activities:

  1. Mobilized to the site
  2. Site Office Setup Completed.
  3. Site Characterization/assessment field sampling and data collection completed.
  4. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted and are currently under review

SMR 014

UNEP CODE: 004 -OO4

LOCATION:  Ogale Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 293815; Northing: 533219

CONTRACTOR: One Specialty P&S Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 27.5% having carried out the following activities:

  1. Mobilized to the site.
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has obtained full regulatory approval for their site characterization report and RAP to commence remedial action.
  5. Continuation of Remediation Works: Ex-situ Treatment Method: Excavation of impacted Trenches, contaminated soil treatment and recovery of free-phase oil.

SMR 015

UNEP CODE: 004 -OO6

LOCATION:  Obajioken Ogale Eleme LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 294413; Northing: 531468

CONTRACTOR: Giolee Global Resources Limited

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 49.5% having carried out the following activities:

  1. Mobilized to site.
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has received full regulatory approval for their site characterization report and RAP to commence remedial action.
  5. The Remediation Action Phase is ongoing:

a) Ex-situ treatment method: Excavation of impacted soils, treatment of contaminated soil, and recovery of free phase oil.

b) In-situ Treatment Method: Biosparging using air compressor systems and installed injection wells.

SMR 016

UNEP CODE: 012-OO1

LOCATION: Omunwanwan Sime Tai LGA         

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 300875; Northing: 525140

CONTRACTOR: Vitruvian Global Resources Limited

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 18% having carried out the following activities:

  1. Mobilized to the site
  2. Office setup Completed
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has obtained conditional regulatory approval for their site characterization report and RAP to commence remedial action.
  5. Commenced Remediation Action Phase: a) Exsitu Treatment method: Excavation of impacted Trenches, contaminated soil treatment and recovery of free-phase oil.

SMR 017

UNEP CODE: 012 – 001

LOCATION:  Omunwanwan  Sime Tai LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 301420; Northing: 527745

CONTRACTOR: Craneburg Construction Company Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 12% having carried out the following activities:

  1. Mobilized to site.
  2. Office Setup Completed.
  3. Biocell Construction completed
  4. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted and is currently under review

SMR 018

UNEP CODE: 015 – 001

LOCATION:  Wiikayako (Well 10) Kpean Khana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 330552; Northing:508627

CONTRACTOR: Katech Construction Co Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 18.5% having carried out the following activities:

  1. Mobilized to site.
  2. Office Setup Completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has obtained conditional regulatory approval for their site characterization report and RAP
  5. Commenced Remediation Action Phase.

a) Ex-situ Treatment Method: Excavation and treatment of impacted soils ongoing

b) In-situ Treatment method: installation of injection boreholes for biosparging ongoing

SMR 019

UNEP CODE: 009 – 004

LOCATION:  Muugborgbara Biara Gokana  LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 309150; Northing: 520168

CONTRACTOR: Jezreel Engineering Services Limited

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 9% having carried out the following activities:

  1. Mobilized to site.
  2. Office Setup completed
  3. Biocell Construction completed
  4. Site characterization/assessment field sampling and data collection completed. Yet to Submit Site characterization report and RAP for review.

SMR 020

UNEP CODE: 009 – 001

LOCATION:  Bara Yiema Kpite Tai LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 309313 ; Northing:521251

CONTRACTOR: Welltime Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 15.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has been given provisional approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction completed
  6. Commenced Remediation Action Phase: a) Exsitu Treatment Method: Excavation of trenches of impacted soil

b) insitu treatment method: Installation of injection boreholes

SMR 020B

UNEP CODE:

LOCATION:  Barabeedom K.Dere Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 309018; Northing: 515567

CONTRACTOR: Chayoobi Nig Ltd

SCOPE SUMMARY: To carry out site characterization/assessment of the site and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 12.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has received provisional approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction ongoing
  6. Yet to commence active remediation works

SMR 021

UNEP CODE: 009 – 010

LOCATION:  Biara Biara Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 309095; Northing: 519574

CONTRACTOR: Satel Construction Nig Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 17.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has been given provisional approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction completed
  6. Commenced Remediation Action Phase: a) Ex-situ Treatment Method: Excavation and treatment of impacted soil.

SMR 022

UNEP CODE: 019 – 001

LOCATION:  Bera-Bera P/L 1 Bera Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 308892; Northing: 517455

CONTRACTOR: Duluidas Nig. Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 9.5% having carried out the following activities:

  1. Mobilized to site.
  2. Office Setup completed
  3. Biocell Construction completed
  4. Site characterization/assessment field sampling and data collection completed. Yet to Submit Site characterization report and RAP for review.

SMR 023

UNEP CODE: 019 – 002

LOCATION: Bera P/L 1-3 Bera Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 308710; Northing: 51822

CONTRACTOR: Acti & Air Power

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 5.5% having carried out the following activities:

  1. Mobilized to site.
  2. Office Setup ongoing
  3. Biocell Construction ongoing
  4. Site characterization/assessment field sampling and data collection completed. Yet to Submit Site characterization report and RAP for review.

SMR 024

UNEP CODE: 019 – 002

LOCATION:  Bera P/L 1-3 Bera Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 308834; Northing: 518084

CONTRACTOR: Roxcon Nigeria Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 17% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has received full approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction completed
  6. Remediation Action Phase ongoing: a) Ex-situ Treatment Method: Excavation and treatment of impacted soil.

SMR 025

UNEP CODE: 019 – 002

LOCATION:  Bera P/L 1-3 Bera Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 308901; Northing: 517994

CONTRACTOR: Barewa Investment Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 21% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has received full approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction completed
  6. Remediation Action Phase ongoing:

a) Ex-situ Treatment Method: Excavation and treatment of impacted soil.

b) In-situ Treatment Method: Biosparging and Bioventing operations ongoing

SMR 026

UNEP CODE: 019 – 012

LOCATION:  Boobanabe P/L 1-2 K.Dere Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 305861; Northing: 515309

CONTRACTOR: Karidav Integrated Services Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 6% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. Awaiting submission of site characterization report and remediation action plan.
  4. Biocell Construction ongoing

SMR 027

UNEP CODE: 019 – 012

LOCATION:   Boobanabe P/L 1-3 K.Dere Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 306006; Northing: 515395

CONTRACTOR: Transcend Construction Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 13% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has received provisional approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction completed
  6. Yet to commence active remediation works

SMR 028

UNEP CODE: 019 – 010

LOCATION: Gior Kpor/Mogho/ K.Dere   Gokana  LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 308845; Northing: 514494

CONTRACTOR: Toledo Engineering Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 5.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup ongoing.
  3. Site characterization/assessment field sampling and data collection have been completed. Awaiting submission of site characterization report and remediation action plan (RAP)

SMR 029

UNEP CODE:  019 – 010

LOCATION: Gior Kpor/Mogho/ K.Dere   Gokana  LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 308553; Northing: 514402

CONTRACTOR: Bussdor and Comp Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 8% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. Awaiting submission of site characterization report and remediation action plan (RAP).
  4. Biocell construction ongoing

SMR 030

UNEP CODE: 019-035

LOCATION:  Kegbara-Kpor Kpor Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 309569; Northing: 514300

CONTRACTOR: Thaworld Global Resources Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 13.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has received provisional approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction completed
  6. Yet to commence active remediation works

SMR 031

UNEP CODE: 019 – 020

LOCATION:  Debon Mogho/Bodo Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 308896; Northing: 513037

CONTRACTOR: Telmac Engineering Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 5.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup ongoing.
  3. Site characterization/assessment field sampling and data collection have been completed. Awaiting submission of site characterization report and remediation action plan (RAP)

SMR 032

UNEP CODE: 019 – 013

LOCATION: Peeteeh/Boobanabe K.Dere Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 305766; Northing:515496

CONTRACTOR: Halliday Global Services

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 10.5% having carried out the following activities:

  1. Mobilized to the site
  2. Completed site office setup.
  3. Site characterization/assessment field sampling and data collection completed. The Characterization Report and RAP have been submitted and are currently under review.
  4. Biocell Construction completed

SMR 033

UNEP CODE: 019 – 013

LOCATION: Peeteeh/Boobanabe K.Dere Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 305451; Northing:515160

CONTRACTOR: Lapideo Multi Services Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage 11% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has received provisional approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction ongoing
  6. Yet to commence active remediation works

SMR 034

UNEP CODE: 019 – 013

LOCATION:  Peeteeh/Boobanabe K.Dere Gokana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting:309522  ; Northing:514282

CONTRACTOR: ZGM Investment Group of Companies Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 5.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup ongoing.
  3. Site characterization/assessment field sampling and data collection have been completed. Awaiting submission of site characterization report and remediation action plan (RAP).

SMR 035

UNEP CODE: 016 – 011

LOCATION:  Kwawa Flowstation & Flare Kwawa Khana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 331632; Northing:509504

CONTRACTOR: Engineering Seven Integrated Konsult Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 8.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup ongoing.
  3. Site characterization/assessment field sampling and data collection have been completed. Awaiting submission of site characterization report and remediation action plan (RAP).
  4. Biocell construction ongoing

SMR 036

UNEP CODE: 016 – 011

LOCATION: Kwawa Flowstation & Flare Kwawa Khana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting:331746  ; Northing:507552

CONTRACTOR: Philcom Integrated Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 55.5% having carried out the following activities:

  1. Mobilized to site.
  2. Office setup completed.
  3. Site Characterization/Assessment field sampling and data collection completed.
  4. Submitted Site characterization report and RAP for review.
  5. The contractor has obtained full regulatory approval for their site characterization report and RAP to commence remedial action.
  6. The Remediation Action Phase is ongoing:

a) Ex-situ treatment method: Excavation of impacted soils, treatment of contaminated soil, and recovery of free phase oil.

b) In-situ Treatment Method: Biosparging around excavated trenches using air compressor systems and installed injection wells.

SMR 037

UNEP CODE: 015 – 001

LOCATION:  Wiikayako (Well 10) Kpean Khana LGA

SITE REFERENCE CO-ORDINATE (UTM WGS 64): Easting: 330433; Northing: 508693

CONTRACTOR: Shearforce Nig Ltd

SCOPE SUMMARY: To carry out site characterization/assessment and remediate hydrocarbon impacted areas within the site.

 STATUS OF WORK ACTIVITIES:

The contractor has achieved a completion percentage of 14.5% having carried out the following activities:

  1. Mobilized to site
  2. Office setup completed.
  3. Site characterization/assessment field sampling and data collection have been completed. The site characterization report and RAP have been submitted.
  4. The contractor has received provisional approval to commence the Remediation phase of the works after the review of documents.
  5. Biocell construction completed
  6. Yet to commence active remediation works
Scroll to Top