STATUS OF COMPLETION OF THE CENTER OF EXECELLENCE FOR ENVIRONMENTAL RESTORATION
S/N | Work Fronts | Target | %Completion | Remarks |
1.00 | Faculty of Vocational Skill Acquisition | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Superstructure | 100 | 100 | Completed |
c | Roof carcass | 100 | 100 | Completed |
d | Plastering | 100 | 100 | Completed |
e | Ceiling grile Work | 100 | 100 | |
f | Electrical conduit | 80 | 90 | |
g | Mechanical conduit | 80 | 90 | |
h | Roof work | 100 | 100 | Completed |
i | Window Installation | 100 | 100 | Completed |
j | Wall screed | 60 | 70 | |
2.00 | Library | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Superstructure (Block works) | 100 | 100 | Completed |
c | Steel Roof work | 100 | 100 | Completed |
d | Electrical conduit | 70 | 90 | |
e | Mechanical conduit | 70 | 90 | |
f | Frame | 100 | 100 | Completed |
g | Roof beam | 100 | 100 | Completed |
h | Ceiling grille | 20 | 50 | |
i | Plastering | 80 | 100 | |
3.00 | Faculty of Environmental Research and Development | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Superstructure (Block works) | 100 | 100 | Completed |
c | Frame | 100 | 100 | Completed |
d | Electrical conduit | 90 | 95 | |
e | Mechanical conduit | 70 | 80 | |
f | Plastering | 100 | 100 | Completed |
g | Roof carcass | 100 | 100 | Completed |
h | Roof covering | 100 | 100 | Completed |
i | Suspended Ceiling | 90 | 100 | |
j | Window installation | 100 | 100 | Completed |
k | Wall Screed | 90 | 100 | |
l | Floor Tiling work | 100 | 100 | Completed |
m | Wall Tiling work | 100 | 100 | Completed |
4.00 | Classroom | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Block wall | 100 | 100 | Completed |
c | Frame work | 100 | 100 | Completed |
d | Roof carcass | 100 | 100 | Completed |
e | Plastering | 100 | 100 | Completed |
f | Electrical conduit | 100 | 100 | |
g | Mechanical conduit | 85 | 90 | |
h | Ceiling grile | 90 | 100 | |
i | Window installation | 100 | 100 | Completed |
j | Roof covering | 100 | 100 | Completed |
k | Floor Tiling work | 100 | 100 | Completed |
l | Suspended ceiling | 85 | 90 | |
m | Screed | 90 | 90 | |
n | Wall Tiling work | 95 | 100 | |
o | Door installation | 40 | 50 | |
5.00 | Students Dormitory (Female) | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Block wall | 100 | 100 | Completed |
c | Frame work | 100 | 100 | Completed |
d | Suspended slab | 100 | 100 | Completed |
e | Roof steel work | 100 | 100 | Completed |
f | Suspended Ceiling | 95 | 100 | |
g | Plastering | 100 | 100 | Completed |
h | Electrical conduit | 90 | 95 | |
i | Mechanical conduit | 70 | 80 | |
j | Roof cover | 100 | 100 | Completed |
k | Floor Tiling work | 100 | 100 | Completed |
l | Wall Tiling work | 100 | 100 | Completed |
m | Wall Screed | 80 | 90 | |
n | Window installation | 100 | 100 | Completed |
o | Door installation | 40 | 60 | |
p | Cable tray Installation | 50 | 70 | |
6.00 | Students Dormitory (Male) | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Superstructure (Block works) | 100 | 100 | Completed |
c | Frame work | 100 | 100 | Completed |
d | Suspended slab | 100 | 100 | Completed |
e | Roof steel work | 100 | 100 | |
f | Suspended Ceiling | 90 | 100 | |
g | Plastering | 100 | 100 | Completed |
h | Electrical conduit | 70 | 80 | |
i | Mechanical conduit | 70 | 80 | |
j | Roof cover | 100 | 100 | Completed |
k | Floor Tiling work | 100 | 100 | Completed |
l | Wall Screed | 80 | 90 | |
m | Window installation | 100 | 100 | Completed |
n | Wall Tiling work | 50 | 70 | |
o | Door Installation | 50 | 50 | |
7.00 | Soldiers Quarters Building: | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Superstructure (Block work) | 100 | 100 | Completed |
c | Roof work | 100 | 100 | Completed |
d | Plastering | 100 | 100 | Completed |
e | Ceiling | 95 | 100 | |
f | Tiling | 100 | 100 | Completed |
g | Painting | 100 | 100 | Completed |
h | Door | 100 | 100 | Completed |
i | Window | 100 | 100 | Completed |
j | Mechanical | 86 | 100 | |
k | Electrical | 86 | 100 | |
8.00 | 3 bedroom Duplex (10 pcs) | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Superstructure (Block works) | 100 | 100 | Completed |
c | Frame | 100 | 100 | Completed |
d | Suspended slab | 100 | 100 | Completed |
e | Electrical conduit | 50 | 60 | |
f | Mechanical conduit | 70 | 80 | |
g | Plastering | 30 | 40 | |
h | Window frame installation | 40 | 50 | |
i | Roof Steel Carcass | 30 | 50 | |
j | Roof Covering | 10 | 30 | |
9.00 | 2 Bedroom Flat 1 (2 pcs) | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Superstructure (Block works) | 100 | 100 | Completed |
c | Frame | 100 | 100 | Completed |
d | Mechanical | 50 | 70 | |
e | Plastering | 50 | 60 | |
f | Window frame installation | 100 | 100 | Completed |
g | Roof carcass | 0 | 0 | |
10.00 | 2 Bedroom Flat 2 (4 pcs) | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Frame | 100 | 100 | Completed |
c | Superstructure (Block works) | 100 | 100 | Completed |
d | Mechanical | 50 | 70 | |
e | Plastering | 70 | 100 | |
f | Window Installation | 25 | 50 | |
g | Roof Steel Carcass | 85 | 100 | |
h | Roof covering | 85 | 70 | |
i | Ceiling grille | 30 | 50 | |
11.00 | 1 Bedroom Flat (4 pcs) | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Frame | 100 | 100 | Completed |
c | Superstructure (Block works) | 100 | 100 | Completed |
d | Mechanical | 70 | 80 | |
e | Plastering | 90 | 100 | |
f | Roof steel work | 100 | 100 | Completed |
g | Window Frame installation | 100 | 100 | Completed |
h | Aluminum roof covering | 100 | 100 | |
i | Aluminum glass | 100 | 100 | Completed |
j | Suspended ceiling | 40 | 50 | |
k | Floor Tiling work | 60 | 60 | |
l | Electrical conduit | 90 | 100 | |
m | Suspended Ceiling grile | 80 | 100 | |
n | Wall screed | 15 | 30 | |
12.00 | Canteen | Sub-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Frame | 100 | 100 | Completed |
c | Mechanical | 70 | 80 | |
d | Roof slab | 100 | 100 | Completed |
e | Block work | 95 | 100 | |
13.00 | Shopping Plaza | Sub-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Frame | 100 | 100 | Completed |
c | Block work | 10 | 50 | |
14.00 | Clinic | Sub-structural/Super-structural work | ||
a | Substructure | 100 | 100 | Completed |
b | Block works | 100 | 100 | Completed |
c | Frame | 100 | 100 | Completed |
d | Plastering | 100 | 100 | Completed |
e | Roof covering | 100 | 100 | Completed |
f | Window installation | 100 | 100 | Completed |
g | Suspended Ceiling grile | 100 | 100 | Completed |
h | Electrical conduit | 100 | 100 | Completed |
i | Mechanical conduit | 70 | 100 | Completed |
j | Wall Screed | 70 | 100 | Completed |
k | Suspended Ceiling | 90 | 100 | completed |
l | Floor Tiling work | 100 | 100 | Completed |
m | Wall Tiling work | 90 | 100 | completed |
15.00 | Fencing/ external work: | Sub-structural/Super-structural work | ||
a | Block work | 100 | 100 | Completed |
b | Excavation/ backfilling | 100 | 100 | Completed |
c | Concrete blinding for fence foundation | 100 | 100 | Completed |
d | Rendering | 20 | 30 | Ongoing |
e | Column/Beam work | 100 | 100 | Completed |
f | Retaining wall | 100 | 100 | Completed |
16.00 | Road Work | Earth work | ||
a | Earth work | 85 | 90 | Ongoing |
b | Asphalts | 80 | 85 | ongoing |
c | Concrete Kerbs | 85 | 90 | Ongoing |
17.00 | DRAINAGE WORK | |||
a | Installation of Precast drain | 90 | 95 | ongoing |
b | External Drainage/Cover | 50 | 60 | ongoing |
18.00 | Admin Block | Sub-structural/Super-structural work | ||
a | Sub-structural Work | 100 | 100 | Completed |
b | Block works | 85 | 100 | completed |
c | Frame | 100 | 100 | Completed |
d | Suspended slab | 100 | 100 | Completed |
e | Electrical conduit | 75 | 80 | ongoing |
f | Mechanical conduit | 70 | 80 | ongoing |
g | Staircase | 100 | 100 | Completed |
h | Plastering | 50 | 50 | Ongoing |
i | Ceiling grille | 30 | 50 | Ongoing |
19.00 | Auditorium | Sub-structural work | ||
a | Sub-structural Work | 100 | 100 | Completed |
b | Super structure (Gallery) | 100 | 100 | Completed |
c | Frame | 100 | 100 | Completed |
d | Electrical conduit | 70 | 80 | Ongoing |
e | Mechanical conduit | 70 | 80 | Ongoing |
f | Roof slab | 100 | 100 | Completed |
g | Block works | 100 | 100 | Completed |
h | Plastering | 90 | 100 | completed |
20.00 | CLUB HOUSE | Sub-structural work | ||
a | Sub-structure | 100 | 100 | Completed |
b | Mechanical conduit | 70 | 80 | Ongoing |
c | Frame | 100 | 100 | Completed |
d | Suspended slab | 100 | 100 | Completed |
e | Roof Slab | 100 | 100 | Completed |
f | Block work | 60 | 70 | Ongoing |
21.00 | GATE HOUSE | Sub-structural/Super-structural work | ||
a | Sub-structure | 100 | 100 | Completed |
b | Suspended slab | 100 | 100 | Completed |
c | Frame | 100 | 100 | Completed |
d | Superstructure (Block works) | 100 | 100 | Completed |
e | Plastering | 100 | 100 | Completed |
f | Wall Screed | 60 | 80 | Ongoing |
g | Electrical conduit | 80 | 90 | Ongoing |
h | Mechanical conduit | 80 | 90 | Ongoing |
i | Window installation | 100 | 100 | Completed |
22.00 | POWER HOUSE | |||
a | Sub-structure | 100 | 100 | Sub-structural work |
b | Frame | 100 | 100 | Completed |
c | Roof Slab | 100 | 100 | Completed |
d | Window installation | 100 | 100 | Completed |
e | Plastering | 100 | 100 | Completed |
f | Block work | 100 | 100 | Completed |
23.00 | WATER BOARD | |||
a | Sub-structure | 100 | 100 | Sub-structural work |
b | Superstructure (Block works) | 100 | 100 | Completed |
c | Frame | 100 | 100 | Completed |
d | Roof slab | 100 | 100 | Completed |
e | Plastering | 100 | 100 | Completed |
f | Electrical conduit | 80 | 90 | Ongoing |
g | Mechanical conduit | 80 | 90 | Ongoing |
h | Window installation | 100 | 100 | Completed |
i | Wall Screed | 45 | 50 | Ongoing |
24.00 | ELEVATED WATER TANK | |||
a | Sub-structure | 90 | 100 | Sub-structural work |
b | Tank stanchion Installation | 80 | 100 | Super-structural work |
25.00 | FIRE FIGHTING WATER POOL/RAW WATER TANK FOUNDATION | |||
a | Sub-structure | 80 | 100 | Sub-structural/Super-structural work |
26.00 | PARKING LOT | |||
a | Parking lot 1 and 2 (inter locks) | 70 | 100 | Completed |
27.00 | EXTERNAL WORK | |||
a | Landscaping (grassing) | 20 | 30 | Ongoing |